Saturday 15 November 2014

Ankaful Psychiatric Hospital Project

This was a big project that is now completed.  We had their water system refurbished so that the different buildings now have water.  The pump was fixed and now pumps to fill several tanks through out the grounds and the water is then gravity fed to the different sites.
 
We also had the laundry equipment repairs as none of it was working and they were having to send everything out to a different location.
Cement work at the Women's quarters was falling apart due to poor drainage so the drainage problems were fixed and new cement poured.  It looks great.  The Church members in 2 Wards volunteered and did some clean up around the place and also painted the Women's quarters.  It now looks so much better.

We also supplied them with some equipment (blood pressure cuffs, stethoscopes, thermometers, oxygen tanks, etc. etc. and bandaging and such.  

We will do the handover ceremony (commission the project) at the end of the month.  We just visited there to make sure all is going well for that. 

Again, they are so grateful for the help from the Church.